Completed Project Activities -
What's Next -
- 2008: Complete draft environmental documents and carry out active outreach program
- 2009: Complete studies, approve technical and environmental documents, begin design
- 2004: Draft Feasibility Report established service areas and scope of program
- 2006: Engineering Feasibility Report established facility needs
- 2007: Pursued grant funding opportunities, refined program scope, and selected consultants for environmental analysis and outreach
What We Are Doing Now -
- Work underway on EIS/EIR
- Moving ahead with full-scale studies; engineering, financial, and economic